We've made a lot of progress in the last week or so. A week ago Thursday, the weather was finally cooperating so we had the mini-excavator dropped off so the real digging could begin. The two trees were cut down earlier in the week, and the tree people left the stumps kinda tall so the excavator could use the leverage to pull them over, all easy-like. Peter started digging around noon on Thursday, but the fir tree stump near the southeast corner of the yard must not have heard that it was supposed to come out easy (like Sunday morning). Consequently, after four hours of clawing and hacking with the excavator, and cutting roots with the Sawzall, Peter finally had the fir stump out of the ground. Here's a photo with the stump in the foreground, and the "heavy" machinery in the background:
After that the trenches could actually be started. It may seem like overkill to have an excavator for this small of a job, but for a total rental fee of around 300 bucks, it was definitely worth it. If we were to dig all of this by hand, it probably would have taken the better part of a week...
The following is a video of the digging in action. My commentary may be a bit overboard (one too many "giant" references) but given the effort that was exerted to remove that stump, the hyperbole came naturally:
The following is a video of the digging in action. My commentary may be a bit overboard (one too many "giant" references) but given the effort that was exerted to remove that stump, the hyperbole came naturally:
With all the digging out of the way, we set to work building the forms. It's kinda tough to build something nice and square when the existing house is... well, slightly crooked. Considering the difficult baseline, I think we made the best of it. We went a bit deeper and a bit wider for the footings than the engineering called for, but one ounce of prevention is worth two lbs in the hand, as they say.
The following is a little video of the concrete pour in action. It may look like we're just sorta watching it flow out, but believe me, there was a lot of shoveling going on. It was a fairly busy 45 minutes there, not to mention the amount of time spent on the concrete finish work after the pour was done. We were lucky that the truck could be backed up this close, as we didn't need to have a separate pumper truck on hand as well.
Which brings us to today: Renée and I stripped the forms and backfilled the foundation, which took us much of the day. We should finally be out of the dirt now, and the fun stuff should begin. Here's a photo of the completed foundation (note that we left one stump in place... it will probably get cut down at some point, but didn't seem necessary right now, given amount of work it would require):
And another view of the foundation... it doesn't seem like much now, but once the second story goes on, the immense grandeur of our home will be readily apparent:
And that's pretty much it for now. Peter will start the framing tomorrow or maybe Tuesday, and in a week or so we'll be done. Thanks for reading.